An email sent to directors and actives from Jim Ljunglin '57 provided an update on the fire sprinkler project. Some points are listed below:
- Work began this morning, August 6.
- Dan, the installer, is running 2 1/2" pipe from the communications room behind the kitchen, over the ice maker, and down the wing.
- After the supply pipe is laid out, work will begin on plumbing and installing sprinklers in the rooms.
- While the sprinkler heads cannot be painted, the pipes, which are currently black, and the fittings, which are currently red, can and likely will be painted the next time the respective rooms are painted.
Thanks for the update, Jim!
As updates are sent out from those involved with the project, they will be posted here. Stay tuned!