An email came down from above today, from Chris Geer at Albany Fire Protection, Inc., via Jay Webb ’61. Here's where the project stands:
- Two workers are currently installing pipe at the house.
- The main supply pipe in the wing is complete, running from the kitchen to wing head.
- All of the piping on the second floor is complete. All to be done is the installation of the sprinkler heads.
- The piping to the third floor is "stubbed," or stopped off for now. The company is planning on doing the entire third floor and then finishing up the first floor.
Thanks for the update Chris and Jay! Of course, updates will be published as they come out. Stick around!